47. Power to require security.–(1) Subject to the provisions of this section, a distribution licensee 
may require any person, who requires a supply of electricity in pursuance of section 43, to give him 
reasonable security, as may be determined by regulations, for the payment to him of all monies which 
may become due to him– 

(a) in respect of the electricity supplied to such persons; or 
(b) where any electric line or electrical plant or electric meter is to be provided for supplying 

electricity to such person, in respect of the provision of such line or plant or meter, 

and if that person fails to give such security, the distribution licensee may, if he thinks fit, refuse to give 
the supply of electricity or to provide the line or plant or meter for the period during which the failure 
continues. 

(2) Where any person has not given such security as is mentioned in sub-section (1) or the security 
given by any person has become invalid or insufficient, the distribution licensee may, by notice, require 
that person, within thirty days after the service of the notice, to give him reasonable security for the 



32 
 

payment of all monies which may become due to him in respect of the supply of electricity or provision 
of such line or plant or meter. 

(3) If the person referred to in sub-section (2) fails to give such security, the distribution licensee may, 
if he thinks fit, discontinue the supply of electricity for the period during which the failure continues. 

(4) The distribution licensee shall pay interest equivalent to the bank rate or more, as may be 
specified by the concerned State Commission, on the security referred to in sub-section (1) and refund 
such security on the request of the person who gave such security. 

(5) A distribution licensee shall not be entitled to require security in pursuance of clause (a) of      
sub-section (1) if the person requiring the supply is prepared to take the supply through a pre-payment 