Central · Act 12 of 2025

Section 7 — Conditions precedent for manufacture of boiler and boiler components.

The Boilers Act, 2025

Read in your languageअपनी भाषा में पढ़ें · Official source versions

Mapped language choices keep this section. Other choices are labelled ‘Complete act’ until section mappings are verified.

Additional official language versions have not been imported for this act yet.

Only available official source versions are shown. Language labels come from source metadata or filenames.

STATUTORY TEXT
Find in this text
No person shall manufacture or cause to be manufactured any boiler or boiler components, or both, unless---

(a) the premises or precincts wherein boiler or boiler components, or both, are manufactured, have such facilities for design and construction as may be specified by regulations;

(b) a certificate for the design and drawings of the boiler and boiler components have been granted by the inspecting authority under clause (a) of sub-section (3) of section 8;

(c) the material, mounting and fitting used in the construction of boiler or boiler components, or both, conform to such specifications as may be specified by regulations; and

(d) the person engaged in welding boiler or boiler components hold welders certificate granted by the competent authority under sub-section (4) of section 6.

आगे पढ़ें / Continue reading

Explore the next section or browse this act in the selected language.

Next · Section 8Inspection during manufacture. →All sections / सभी धाराएँThe Boilers Act, 2025 →
More sections of this actSection 1 · Short title, commencement and application.Section 2 · Definitions.Section 3 · Central Boilers Board.Section 4 · Technical Adviser.Section 5 · Chief Inspector, Deputy Chief Inspector and Inspector.Section 6 · Competent authority to grant welders certificate.Section 8 · Inspection during manufacture.Section 9 · Inspection during erection.
Source and version

India Code, Government of India. Text fetched 17 Oct 2026. Source metadata reports last modification: 2025-07-14. Check the linked official text and subsequent notifications when applying a provision.

Share this section

Section 7 — Conditions precedent for manufacture of boiler and boiler components. | The Boilers Act, 2025 | NYAYA SIGNAL

Share the card with this clickable reading link. पढ़ें और अगली धारा देखें।

NYAYA SIGNAL · Free access · Official source references

· Saves and reading positions stay on this device.