21. (1) A Participating Department may, by itself or in collaboration with one or more of the participating departments as the case may be, prepare Project Plans for one or more elements of the Braj Development Plan.
(2) Various participating departments in the district, receiving grants, loans or budget sanctioned by the State Government, shall ensure convergence/co-ordination of their departmental schemes with the schemes/projects under the Braj development Plan.

आगे पढ़ें / Continue reading

Explore the next section or browse this act in the selected language.

Next · Section 22Grants and loans by the Government →All sections / सभी धाराएँTHE UTTAR PRADESH BRAJ (TEERTH VIKASH PARISHAD) ACT, 2015 →
More sections of this actSection 1 · Short title, extent and commencementSection 2 · DefinitionsSection 3 · Constitution and Incorporation of the ParishadSection 4 · The Chief Executive OfficerSection 5 · The Executive CommitteeSection 6 · Composition of the Braj Planning and Development SamitiSection 7 · Power to co-optSection 8 · Headquarters of the Parishad
Source and version

India Code, Government of India. Text fetched 18 Oct 2026. Source metadata reports last modification: 2025-02-04. Check the linked official text and subsequent notifications when applying a provision.

Share this section

Section 21 — Preparation of the Project Plan co-ordination and convergence | THE UTTAR PRADESH BRAJ (TEERTH VIKASH PARISHAD) ACT, 2015 | NYAYA SIGNAL

Share the card with this clickable reading link. पढ़ें और अगली धारा देखें।

NYAYA SIGNAL · Free access · Official source references

· Saves and reading positions stay on this device.